Città (phase 3)

Customer
Construgep
Location
Montréal
Timeline
2022-2024
Multifamily

This Construgep project at the intersection of Rue Viau and Rue Jean-Nicolet in Saint-Léonard includes a total of 177 units in two towers.

Our task

ORAM was contracted to install the following plumbing systems:

  • Sanitary drainage system
  • Rainwater drainage system
  • Domestic cold water piping
  • Centralized domestic hot water system
  • Natural gas piping

ORAM Expertise

To help reduce project costs, our team modified the designs for the hot and cold water systems as well as the drainage system:

  • Distribution method and pipe layout
  • Pressure management
  • Specialized equipment proposals
  • Trade coordination

Statistics

78,000
litres of rainwater to drain
7,100
litres of hot water per hour
Città E